COMMISSIONING PLAN OF WASTE TREATMENT SYSTEMS
SUBJECT MUST PREPARE COMMISSIONING PLAN OF WASTE TREATMENT SYSTEMS
Project owners which is subject to investment in the construction/ instalation of waste treatment systems (including: wastewater, dust, exhaust gas, solid wastes and hazardous wastes) as regulated must prepare a commissioning plan of waste treatment systems according to the provisions of Clause 9, Article 1, Decree 40/2019/ND-CP, supplementing Article 16b, Decree 18/2015/ND-CP.
TIME FOR PREPARING COMMISSIONING PLAN OF WASTE TREATMENT SYSTEMS
Under the provisions of Clause 9, Article 1, Decree 40/2019/ND-CP supplementing Clause 2, Article 16b, Decree 18/2015/ND-CP, the project owner which is subject to investment in construction and installation of waste treatment systems are only put the waste treatment systems into commissioning together with the commissioning of the entire project or for each investment phase of project (if the project is divided into investment phases) or put the waste treatment work of the project when all the conditions below are satisfied:
- Waste treatment systems have been completed in accordance with the approval decision of EIA report or approval decicision of modified EIA report (if any)
- The installation of automatic and continuous waste monitoring equipment, system has been completed to monitor the quality of wastewater and emissions as legal requirements;
- Waste treatment systems have operating process meeting environmental protection requirements;
- As-built documents of waste treatment systems have been transferred and accepted as legal requirements of construction. The project owner shall take legal responsibility for the completed dossiers of waste treatment systems;
- Prepare and send a commissioning plan of waste treatment systems of the project to the environmental protection authority of province where the project ís located in and the EIA report approval authority at least 20 working days before the commencement date of commissioning. The form of a commissioning plan of waste treatment systems is specified in form No. 09, Appendix VI, Section I issued in this Decree.
- Thus, the project owner must prepare a commissioning plan of waste treatment systems right after completing the construction, installation of the waste treatment systems.
THE AUTHORITY AGENCY RECEIVE THE COMMISSION PLAN OF WASTE TREATMENT SYSTEMS
Under the provisions of Clause 9, Article 1, Decree 40/2019/ND-CP supplemented at Clause 2d, Article 16b, Decree 18/2015/ND-CP, the authority agency recieve the commissioning plan of waste treatment systems as belows:
- The environmental protection authority of province where the project is located in;
- The EIA report approval authority.
Under the provisions of Clause 9, Article 1, Decree 40/2019/ND-CP supplemented at Clause 2d, Article 16b, Decree 18/2015/ND-CP, the authority agency who inspects waste treatment systems is the environmental protection authority of province where the project is located in.
CONTENT OF A COMMISSIONING PLAN OF WASTE TREATMENT SYSTEMS
The form and contents of a commissioning plan of waste treatment systems is prepared according to the Form No. 09, Appendix VI, Section I, Appendix of Decree No. 40/2019/ND-CP, including:
- General information about the project implementation process;
- List all waste treatment systems required construction, instaltion in details as required under decision on approval for (modified) EIA report;
- Results of completed waste treatment systems for commissioning (including all ittems or each item), including:
- A detailed report of each system/equipment including wastewater collection, treatment; dust, emission treatment; storage, treatment of non-hazadous solid wastes, hazardous wastes; environmental incident prevention and response; ….
- Expected water balance during project operation is calculated for wastewater;
- A detailed commissioning schedule of completed waste treatment system of the project, including commencement time, completion time, …
- Plan for waste monitoring; performance assessment of waste treatment system, equipment;
VIECA’S EXPERIENCE
VIECA is a prestigious unit with many years of experience in preparing the commissioning plan of waste treatment systems.
Being a member unit of Vinacontrol Group with high reputation and professionalism.
Extensive experience in coordinating and working with central and local government agencies.
HERE ARE SOME TYPICAL PROJECTS FOR PREPARING COMMISSIONING PLANS OF WASTE TREATMENT SYSTEMS CONSULTED BY VIECA.